WPI was retained by Costco Wholesale, Inc. to build a new fueling facility at its Santa Clarita facility. The facility was designed to dispense over 1,000,000 gallons of fuel per month.  WPI’s scope of work included:

 

  • Removed existing asphalt and recycling it at a reclamation facility
  • Installation of shoring and excavation of underground storage tank (UST) pit
  • Installation of three 30,000 gallon USTs, double walled fiberglass product piping, six product dispenser islands, state of the art UST and product dispenser monitoring systems and associated electrical equipment/conduits, etc.
  • Installation of a new dispenser island canopy (including construction of new concrete footings)
  • Backfilling and compaction of all excavations and replacement of removed concrete and asphalt
  • Performing all necessary fueling system testing, including UST compliance testing witnessed by the local Certified Unified Program Agency (CUPA)

 

WPI personnel who completed this work hold the following installation and equipment certifications:

 

  • Smith Fibercast
  • Bravo
  • Healy
  • Containment Solutions
  • Xerxes USTs
  • ICC UST Installer / Vapor Recovery

WPI completed the work within the original calendar day timeline established by Costco despite two weeks of weather delays.